2006 Bond Projects (updated April 2008)
|
New Facilities
- Elementary 30
- Elementary 31
- Elementary 32
|
- Elementary 33 (design only)
- Junior High 11
- Junior High 12
|
|
Existing Facilities
Bear Creek Elementary
- Replace Brick (Completed)
- Above Ceiling Package (Completed)
- Bathroom floor and wall finish replacement (Completed)
Cimarron Elementary
- Secure front entrance by adding storefront walls and doors at the ends of two corridors leading from front entry to classroom areas. (Completed)
- Bathroom floor and wall finish replacement
Fielder Elementary
- Replace carpet and flooring in entire building (Completed)
- Bathroom floor and wall finish replacement
Golbow Elementary
- Replace all exterior doors (Completed)
Hayes Elementary
- Replace carpet and flooring in entire building (Completed)
- Bathroom floor and wall finish replacement
Katy Elementary
Mayde Creek Elementary
- Above ceiling package
- Bathroom floor and wall finish replacement
- 10 classroom addition
Memorial Parkway Elementary
- Replace carpet and flooring in entire building (Completed)
- Reconfigure administrative office area for visual control of building entrance, and meet program needs for conference space and clinic space, Need an automatic door opener sensor for students/teachers in wheelchairs
- Bathroom floor and wall finish replacement
Nottingham Country Elementary
- Emergency generator and associated equipment (Completed)
- Secure front entrance by adding storefront walls and doors at the ends of two corridors leading from front entry to classroom areas (Completed)
Pattison Elementary
- Replace low-sloped roof areas
- Replace all exterior doors (Completed)
Sundown Elementary
- Bathroom floor and wall finish replacement
- Above ceiling package
- 10 classroom addition
Winborn Elementary
- Above ceiling
- Secure front entrance by adding storefront walls and doors at the ends of two corridors leading from front entry to classroom areas. (Completed)
Wolfe Elementary
Beck Junior High
- Modifications to existing CATE Technology Education Lab (Completed)
Katy Junior High
- Replace Roof
- Establish CATE Technology Education Lab (Completed)
McDonald Junior High
- Replace the McQuay chillers (Completed)
- Replace Roof
- Establish CATE Technology Education Lab (Completed)
Memorial Parkway Junior High
Katy High School
- Stadium lighting upgrade & replacement (Completed)
- Replace PoolPak Air Handler (Completed)
- Baseball Facility Renovation - concession, bleachers, fencing (ADA Compliant) (Completed)
- Enlarge existing weight room at field house
- KHS Mechanical Equipment Replacement.
Mayde Creek High
- Sewer and Water Well Equipment Replacement
- Build new natatorium on site
- Replace select exterior doors and hardware (Completed)
- Replace domestic hot water heater in Athletics (Completed)
- Waterproofing (Completed)
Morton Ranch High School
Taylor High School
- Baseball Facility Renovation - concession, bleachers, fencing (ADA Compliant) (Completed)
- Domestic boiler and kitchen A/C upgrade
Miller Career & Technology Center
- Renovation and expansion of existing facility
Opportunity Awareness Center
- Renovation and expansion of existing facility to include School of Choice and Behavior Transition Program
East Transportation Center
| |